What should a construction draw schedule look like?

A draw schedule ties payments to completed milestones rather than the calendar. Structured well it keeps a builder cash-positive through the job. Structured badly it funds the client's project with the builder's money.

By the BYLD team. Last updated 10 November 2026.

The principle: get paid for work before you perform the next work

A draw schedule is a cash flow instrument, not a billing formality. The builder pays trades and suppliers continuously; the client pays in discrete chunks. The gap between those two is financed by someone, and a poorly structured schedule means it is financed by the builder.

The test for any draw schedule is simple. Walk it stage by stage and ask what your cash position is at each point, assuming trades are paid on their normal terms. If you go meaningfully negative at any stage, the schedule is wrong, no matter how reasonable it looks on paper.

A typical residential structure

An illustrative eight-draw residential schedule. Actual percentages vary with scope, region, and lender.
DrawMilestoneTypically released when
DepositContract signingContract executed. Often covers preconstruction and initial ordering
1Permits and mobilizationPermits pulled, site prepared, temporary services in
2Foundation completeFootings and foundation poured and inspected
3Framing completeStructure framed and framing inspection passed
4Dry-inRoof, windows, and exterior doors in. Building is weather-tight
5Rough-inMechanical, electrical, and plumbing rough-in inspected
6Drywall and insulationInsulation inspected, drywall hung and finished
7FinishesCabinetry, flooring, trim, fixtures installed
8Final completionCertificate of occupancy issued, punch list closed, retainage released

Where draw schedules go wrong

What to submit with a draw request

The draws that get funded fastest are the ones the reviewer does not have to ask questions about. Submit a consistent package every time:

Assembling that by hand each time is where most of the administrative cost sits. If the photos, budget, and change orders already live in one system, the draw package is mostly a report rather than a research project. In BYLD, photos, the budget and change orders sit on the same project, so the backup for each draw is already in one place.

Common questions

What is a construction draw schedule?

A draw schedule is the agreed sequence of payments across a construction project, tied to completed milestones rather than dates on a calendar. Each draw is released after the corresponding stage of work is finished and, on a financed project, after a lender inspection confirms it.

What are typical construction draw stages?

A common residential structure runs: deposit at contract signing, permits and mobilization, foundation complete, framing complete, dry-in with roof and windows, mechanical electrical and plumbing rough-in, insulation and drywall, interior finishes and cabinetry, and final completion with certificate of occupancy. The number of draws typically ranges from five to ten.

How much should the final draw be?

Large enough that the client remains motivated to complete closeout, and small enough that the builder is not financing the last month of work. Retainage of five to ten percent held until punch list completion is common. A final draw so large that the builder is deeply negative through finishes is the most common structural flaw in a draw schedule.

Who approves a construction draw?

On a financed project the lender approves after an inspection verifying the milestone is complete. On a cash project the homeowner approves directly. Either way the builder should submit the same package: the completed scope, supporting photos, lien waivers from the trades paid out of that draw, and updated budget status.

Tie draws to the schedule