What should a construction draw schedule look like?

A draw schedule ties payments to completed milestones rather than the calendar. Structured well it keeps a builder cash-positive through the job. Structured badly it funds the client's project with the builder's money.

By the BYLD team. Last updated 13 August 2026.

The principle: get paid for work before you perform the next work

A draw schedule is a cash flow instrument, not a billing formality. The builder pays trades and suppliers continuously; the client pays in discrete chunks. The gap between those two is financed by someone, and a poorly structured schedule means it is financed by the builder.

The test for any draw schedule is simple. Walk it stage by stage and ask what your cash position is at each point, assuming trades are paid on their normal terms. If you go meaningfully negative at any stage, the schedule is wrong, no matter how reasonable it looks on paper.

A typical residential structure

An illustrative eight-draw residential schedule. Actual percentages vary with scope, region, and lender.
DrawMilestoneTypically released when
DepositContract signingContract executed. Often covers preconstruction and initial ordering
1Permits and mobilizationPermits pulled, site prepared, temporary services in
2Foundation completeFootings and foundation poured and inspected
3Framing completeStructure framed and framing inspection passed
4Dry-inRoof, windows, and exterior doors in. Building is weather-tight
5Rough-inMechanical, electrical, and plumbing rough-in inspected
6Drywall and insulationInsulation inspected, drywall hung and finished
7FinishesCabinetry, flooring, trim, fixtures installed
8Final completionCertificate of occupancy issued, punch list closed, retainage released

Where draw schedules go wrong

What to submit with a draw request

The draws that get funded fastest are the ones the reviewer does not have to ask questions about. Submit a consistent package every time:

Assembling that by hand each time is where most of the administrative cost sits. If the photos, budget, and change orders already live in one system, the draw package is mostly a report rather than a research project. That is how BYLD handles draws: project balance, payments, receipts, and change orders sit against the same project, so the package assembles from data that is already there.